Hymus Boulevard, Pointe-Claire QC
April to November 2018
Contract value: +/- $7.2 M
Project consisting of repairs to Hymus Boulevard between Manfred and Delmar Avenues as well as the addition of storm water retention basins.
These works were competed in 5 stages and entailed redoing the boulevard’s infrastructure, sewer mains and aqueducts, the construction of 2 retention basins as well as installation of lamp posts and traffic lights. This all needed to be done within a very tight schedule and as such, required day and evening shiftwork. Paving of the final coat will be done in 2019.
Statistics:
• 1000 m of aquaduct conduits
• 1000 m storm water mains
• 2 retention bassins (2250 m² & 3000 m²)
• Paving surface = 17 000 m²
• 8,000 tons of pavement
• 56,000 tons of stone
• Grass surface = 15,000 m²
• Bicycle path = 1.2 km
• Concrete curb = 1 km
• Concrete sidwalk = 1.7 km